The Seattle Department of Transportation (SDOT) advises travelers of early preparatory work associated with the West Phase of the Mercer Corridor Project on Republican Street between 8th Avenue N and SR 99 beginning Wednesday, April 10 for approximately three weeks.
Republican Street between 8th Avenue N and SR 99 will be restricted as crews complete signal work at the intersection of 9th Avenue N and Dexter Avenue N. Eastbound and westbound traffic on Republican Street will be routed around the work zone and one lane in each direction will be maintained at all times. Work will occur weekdays, 9:00 a.m. to 4:00 p.m.
Please note, on-street parking on the north and south sides of Republican Street between 8th Avenue N and SR 99 as well as the west side of Dexter Avenue N between Republican Street and Mercer Street will be restricted during this work. Access to businesses and alleyways will be maintained.