To minimize traffic impacts, Sound Transit’s contractor rescheduled the sidewalk construction along Montlake Blvd. during the University of Washington’s spring break. During the week of March 22, 2010 there will be several construction activities along Montlake Blvd. adjacent to Husky Stadium that will affect the roadway and sidewalks.
Work and traffic impacts (schedule is subject to change):
March 23 – 25: Complete curb and sidewalk at the new Pacific St. driveway entrance to the Husky Stadium Parking lot.
Sidewalk closure on the east side of Montlake Blvd adjacent to the UW Station construction area (Bicyclist/Pedestrians detour located on the west sidewalk on Montlake Blvd).
Off-peak northbound lane closure on Montlake Blvd (This work will be done Tuesday, March 23 between 10 a.m. and 3 p.m. to minimize traffic impacts)
For more information: Wilbert Santos at (206) 370-5516 or wilbert.santos@soundtransit.org
www.soundtransit.org/UWstation