SDOT crews plan to make repairs on several city of Seattle bridges next week. The schedule is subject to change in the event that other unplanned, urgent needs arise.
Queen Anne Bridge, Jan 19-21—a crew will make concrete repairs on the Queen Anne Bridge, Tuesday through Thursday, from 9 a.m. and 2:30 p.m. each day. One lane of traffic will remain open in each direction.
Emerson Street Overpass, Jan 19-23—crews will repair the concrete deck of the Emerson Street overpass which crosses 15th Avenue West. The westbound, left lane will be closed from 9 a.m. to 3:30 p.m. each day.
Fremont Bridge, Jan 20—the northbound, right curb lane will be closed from 9 a.m. to 2:30 p.m. for maintenance work.
Ballard Bridge, Jan 20-22, and Jan 25-26—the southbound, right lane on the Ballard Bridge will be closed from 10 a.m. to 2:30 p.m. each day to complete guard rail repairs.
First Ave South over the Argo Rail Yard, Jan 21—the southbound, right curb lane will be closed from 9 a.m. to 2:30 p.m. for inspection.
For more information: (206) 684-ROAD (684-7623)
Media contact: (206) 684-8548